Holcim SA – E&I

Electrical, Control & Instrumentation installation works for Holcim Dudfield

Booysendal – Lydenburg

Electrical and Instrumentation installation at Booysendal UG2 North – Process Areas. Installation of 239,662 m of Cables and 12,954 m of Racking.

Assmang Blackrock – N. Cape

Electrical, Control and Instrumentation installation Surface Works. Installed 74,937 m of Cables and 3,385 m of Racking.

Kusile Power Station Waste Water Treatment Plant

Supply, fabricate and erect 530 Tons of Structural Steelwork, 60Tons of Platework, and 8 200m of Piping. Installation of 200 Tons of Mechanical Equipment.

Xstrata Lion Phase 2 Project

Erection of Structural Steelwork and Platework for Furnace Building.

SMPP Project

Supply, fabricate, and erection of 3,000 Tons of Structural Steelwork, 950 Tons of Platework and 33,000m of Piping. Installation of 700 Tons of Mechanical Equipment.

Zondagsfontein Colliery – E&I

Construction of MV/LV reticulation

Twistdraai Colliery – Tubelisha Shaft Project

Supply & Install Conveyor Structural Steel & Free Issue Mechanical Equipment.

Medupi Coal Stockyard Project

Supply, Fabricate and Install Conveyor Steelwork & Free Issue Mechanical Equipment.

Medupi Grootegeluk Expansion Project

Supply, Fabricate, Corrosion Protection, and erection of Structural Steel, Platework & Piping. Installation of Mechanical Equipment. Wet, dry and rom and filter plant.

Air Cooler Condenser for Kusile Power Station

Supply, fabricate and erection of 15,500Tons of Structural Steelwork, 12,000 Tons of Platework and 250 Tons of Piping and 115,000m² of Cladding. Installation of 42,000 Tons of Mechanical Equipment.

Turbine Steelwork for Kusile Power Station

Supply, fabricate and erection of 13,500 Tons of Structural Steelwork and 38,200m² of Cladding for six turbine units.

Khumani Iron Ore Mine BKM Project

Supply, Fabrication, Corrosion, Protection, Delivery to site of Structural Steel & Platework. Erection of Free Issue Mechanical Equipment and Weba Chutes.

Sishen Expansion Project

Supply, fabricate and erection of Structural Steelwork, Platework and Piping.

Sishen South Project

Install Conveyor Steelwork & Mechanicals.

Lumwana Copper Project

Erection of Structural Steelwork and Platework. Installation of Mechanical Equipment, Electrical and Instrumentation.

KILN 2 Upgrade Project – Raw Mill Ducting & Pan, Bucket Conveyors

Supply, Fabricate & Erection of Structural Steelwork plus dismantling and installation of Mechanical Equipment, Silos, Bins, Ducting and Piping. Electrical & Instrumentation Supply, Installation & Commissioning.

Roodepoort Mill 8 Project

Erection of Structural Steelwork and Platework. Installation of Mechanical Equipment, Electrical and Instrumentation.

SA Chrome Horizon

Fabricate, supply and erection of 2,250 Tons of Structural Steelwork, 600 Tons of Platework, 5,000m of Piping and installation of 450 Tons of Mechanical Equipment. Fabricate and assembling of the Chrome Furnaces as well as the Sintering Building and the erection of Sintering Machine.

F4/PS2 Furnace & Palletising / Sintering Plant

Supply, fabricate and erection of 3,000 Tons of Structural Steelwork, 800 Tons of Platework, 8,500m of Piping and the installation of 450 Tons of Mechanical Equipment for Furnace Number 4 and the Sintering Plant.

Xstrata Lion Project

Erection of Structural Steelwork and Platework.

International Ferro Metals Furnace

Supply, Fabricate and Erection of Structural Steelwork for the two Furnace Buildings.

Bokomoso Wonderkop Sinter Plants

Supply, Fabricate and Erection of the complete Sinter Building for two Pellitising Machines and the complete Mechanical Erection for two Sintering Furnaces together with the ancillary buildings and installation of Mechanical Equipment including, Conveyors and Bins. The Complete Electrical and Instrumentation for both Sintering Furnaces and Ancillary Buildings.

Sinter Furnace & Palletising Plant

Supply, fabricate and erection of Structural Steelwork for two Furnace buildings, adjacent buildings, Conveyors, Piping and installation of Mechanical Equipment. Erection of the Sintering/Palletising. Complete installation of the electrical and instrumentation for the Sintering Furnace and the adjacent buildings.

ASA Metals Furnace 3 and 4

Erection of Structural Steelwork and Platework. Installation of Mechanical Equipment.

Kalagadi Main Shaft and Vent Headgear

Supply, fabricate and erection of 650 Tons of Structural Steelwork and 38 Tons of Platework.

Mortimer Expansion and Larox

Erection of 1,200 Tons of Structural Steelwork and 180 Tons of Platework. Installation of 250 Tons of Mechanical Equipment, 3,500m² of Cladding and 15,300m of Piping.

Polokwane Smelter

Erection of 5,300 Tons of Structural Steelwork and 500 Tons of Platework. Installation of 850 Tons of Mechanical Equipment, 23,600m² of Cladding and 3,800m of Piping. Erection for two complete Flash Dryers together with adjoining Conveyors, Transfer Towers and Concentrate Storage Facilities.

Western Limb Tailings Retreatment

Erection of 1,500 Tons of structural steelwork and 80 Tons of platework. Installation of 85 Tons of mechanical equipment and 55km of piping.

PP RUST North Expansion Phase 1 – 600KTPM Concentrator Project

Supply, fabricate and erection of 3,800 Tons of Structural Steelwork, 880 Tons of Platework, 18,000m of Piping, 4,300m²of Cladding and installation of 2,515 Tons of Mechanical Items for the ROM Materials. Handling and Electrical and Instrumentation.

Amandelbult 75-210 KTPM Plant Upgrade

Supply, fabricate and erection of 3,800 Tons of Structural Steelwork, 880 Tons of Platework, 18,000m of Piping, 4,300m² of Cladding and installation of 2,515 Tons of Mechanical Equipment.

Waterval Tetrofit – MIG & UFG Project

Erection of Structural Steelwork and Platework. Installation of Piping and Mechanical Equipment.

Amandelbult A Frame Project

Supply, fabricate and erection of 670 Tons of Structural Steelwork, 329 Tons of Platework, 5,750m of Piping, 6,610m² of Cladding and the installation of 125 Tons of Mechanical Equipment.